Milestone Dates
July 11 ‘05 Start Construction
September 05 Geothermal Drilling starts
October 05 Concrete Foundations starts
February 06 Erect Structural Steel starts
January 06 Above Ground Masonry starts
May 06 Glazing starts
May 06 Roofing starts
November 06 Roofing complete
August 15 ’07 Substantial Completion Building
July 5 ’07 Start Phase 2 (Demo Existing RMHS and install Athletic Fields)
August 08 Finish Phase 2