'bout time.

Richard Montgomery High School
Milestone Dates


July 11 ‘05 Start Construction

September 05 Geothermal Drilling starts

October 05 Concrete Foundations starts

February 06 Erect Structural Steel starts

January 06 Above Ground Masonry starts

May 06 Glazing starts

May 06 Roofing starts

November 06 Roofing complete

August 15 ’07 Substantial Completion Building

July 5 ’07 Start Phase 2 (Demo Existing RMHS and install Athletic Fields)

August 08 Finish Phase 2

[ source | RMPTSA Listserv ]